Time-lapse: Demolition update 7/31 through 8/6 Published on August 06, 2026 Demolition is officially complete at the future Weld County Justice Center, with all buildings now removed from the project site. Tagged as: , Project Update
Time-lapse: Demolition update 7/23 through 7/31 Published on July 31, 2026 Progress continued on the future Weld County Justice Center site this week as demolition nears the end on the north half of the West Block. Tagged as: , Project Update
Defining Fiscal Responsibility: Funding the Weld County Justice Center Published on July 30, 2026 From the earliest conversations about a new courthouse, commissioners have discussed how the project would ultimately be funded. As the project moves closer to construction, the board must determine the funding path that best balances the county's current resources with its long-term financial health. Three funding options are currently under consideration. Tagged as: , Project Update
Time-lapse: Demolition update 7/3 through 7/23 Published on July 24, 2026 Progress continued on the future Weld County Justice Center site this week as demolition progresses on the north half of the West Block. Tagged as: , Project Update
CM/GC Request for Proposals Released Published on July 07, 2026 Weld County has released a Request for Proposals (RFP) seeking qualified Construction Manager/General Contractor (CM/GC) firms to provide preconstruction and construction services for the new Weld County Justice Center in downtown Greeley. Tagged as: , Project Update
Time-lapse: Demolition update 6/25 through 7/1 Published on July 02, 2026 Progress continued on the future Weld County Justice Center site this week as demolition progresses on the north half of the West Block. Tagged as: , Project Update
Time-lapse: Demolition update 6/19 through 6/25 Published on June 25, 2026 Progress continued on the future Weld County Justice Center site this week as demolition shifted to the north half of the West Block. Tagged as: , Project Update
Time-lapse: Demolition update 6/11 through 6/18 Published on June 19, 2026 View the weekly time-lapse video from 6/11 through 6/18. Tagged as: , Project Update
Demolition Activity Begins Published on June 12, 2026 This week, the City of Greeley began demolition of the former Greeley United Methodist Church as well as the house to the west. Tagged as: , Project Update
June 11, 2026, Weld Commissioners' work session with County Council Published on June 11, 2026 Weld County Commissioners held a work session with members of the county council to provide information regarding the new Weld County Justice Center. Tagged as: , Project Update